-
DESTINATION MOON: A History of the
Lunar Orbiter Program
-
-
- CHAPTER X: MISSIONS IV AND V: THE
LUNAR SURFACE EXPLORED
-
- The End of the Operational
Phase
-
-
-
- [297] On September 2
Homer E. Newello Associate Administrator for Space Science and
Applications, certified that the fifth mission was an unqualified
success according to prelaunch objectives. Deputy Administrator
Robert C. Seamans, Jr., concurred on September 6. Both NASA
officials also assessed the whole program as successful; five
missions had been flown out of five planned.48 Indeed the final Orbiter had capped an impressive
effort by the Office of Space Science and Applications to bring
man closer to stepping down upon the lunar soil and understanding
where it was that he would be landing in the near future.
-
- The status of the fifth Lunar Orbiter
remained good following termination of readout early on the
morning of [298] August 27. Lunar
Orbiter II and III also continued to
orbit the Moon and to provide extensive data on the lunar
environment and its gravitational field. These three spacecraft
served the Manned Space Flight Network as tracking targets for
training personnel who would track Apollo.49
-
- Lunar Orbiter II had sufficient attitude control gas to survive until
early November. Ground control operators planned to impact it into
the Apollo zone on the Moon's surface even though analysis of
tracking data indicated that it could probably remain in orbit one
or two years. longer. Once the spacecraft lost its attitude
control gas, however, it would become a derelict in orbit, beyond
the control of ground operations. Program officials deemed it
necessary, therefore, to crash the spacecraft while they could, to
avoid any potential communications interference in future manned
missions. They also planned to lower Lunar Orbiter III's
apolune to make its orbit as circular as possible for further
training for Apollo tracking. However, expiration of its gas would
soon mean that it, too, would have to be crashed.
-
- The fifth Orbiter had just begun its
extended mission late in August. Its orbit would be changed on
October 10 so [299] that it might better survive the umbral eclipse of
October 18. (Program engineer Leon J. Kosofsky and mission
operators changed the orbit so that the spacecraft would pass
through the eclipse and solar occultation by the Moon at the same
time.) Apollo network trackers would continue to track the
spacecraft as long as possible to increase their experience in
preparation for manned lunar missions.50
-
- On September 11 the Lunar Orbiter Program
Office issued a statement of the plans for terminating the life of
the three remaining Orbiters. It stated briefly:
-
- The policy is to track the Orbiter
spacecraft until the approach of loss of attitude control as
indicated by the nitrogen pressure. While the spacecraft is still
controllable, the engine will be fired so as to cause impact with
the lunar surface. The impact will be made within the Apollo zone
if feasible. At this time, it appears that Orbiter II will be
impacted in early November, Orbiter III in mid October, and
Orbiter V in mid summer 1968. Contact with Orbiter IV has been
lost.51
-
- Following the final acquisition of all
Lunar Orbiter V photographic data, Lee R. Scherer issued a summary
statement about the program's achievements. Among these he
stressed that Lunar Orbiter
II photography had led to the
identification of the Ranger
VIII impact point on the Moon.
Orbiter III [300] photography had Identified Surveyor I on the
Moon's surface. The locations of the other Surveyors were also
determined by using Orbiter photography. The fifth Orbiter had
photographed major lunar features of scientific interest at a
resolution 100 times better than Earth-based telescopes could
achieve under ideal observation conditions. All Orbiters combined
had photographed the entire lunar surface at a better resolution
by at least an order of magnitude than Earth-based telescopes
could attain and had surveyed the heavily cratered far side of the
Moon. The spacecraft had provided valuable data contributing to
the determination of the Moon's gravitational field. Finally, one
of the program's most significant accomplishments had been to
advance the Apollo Program in a way other than photographic site
certification.
-
- Five Orbiters had enabled the Manned Space
Flight Network to train personnel in tracking and to check out
equipment and computer programs for the manned lunar missions
beginning with Apollo
8 in December 1968 and including
Apollo 10 through 17, of which all but
Apollo 10 and 13 landed on the
Moon. (Apollo 10 tested the complete spacecraft in lunar orbit and
Apollo 13 aborted its landing mission because an onboard
oxygen tank exploded in cislunar space.) The Office of Manned
Space Flight could not have obtained the needed tracking
experience at a timely date [301] if NASA had not
flown the five Lunar Orbiter spacecraft.52
-
- The chronology of the Lunar Orbiters
concluded by the end of January 1968. On October 9, 1967, flight
controllers commanded Lunar Orbiter
III to impact on the Moon. On
October 11 they commanded Lunar
Orbiter II impact. They had lost
communications with Lunar Orbiter
IV on July 17, 1967, and assumed
that its orbit had decayed sufficiently to permit it to crash onto
the Moon late in October, but had no evidence confirming this.
Lunar Orbiter V continued to fly its extended mission until,
unexpectedly, it experienced an anomaly which threatened its orbit
safety. A sudden loss of pressure in the nitrogen tank forced
flight controllers to impact the spacecraft prematurely on the
Moon to avoid losing it in orbit. They conducted this final
maneuver on January 31, 1968, crashing Lunar Orbiter V near the
equator on the Moon's western limb. The impact brought the
operational phase of the Lunar Orbiter Program to a
close.53
-
-
-

